|
Surface Preparation
: The cavity where
the Perlite insulating concrete
is to be filled must first
be thoroughly cleaned and
all existing siporex blocks/concrete
traces must be removed.
Waterproofing
of RCC base (E) :
After cleaning of the
surface of the RCC base
the surface must be thoroughly
wetted. This is a definite
pre requisite and is required
to ensure that all the
capillaries, pores, etc
in the in the RCC base
has been filled with water.
On this wetted surface,
Koster’s NB 1 system
will be brush applied.
Koster’s NB 1 system
consists of hydraulically
reactive powders which
on contact with water
will react and form a
silicate thus effectively
plugging all pores and
capillaries forming a
watertight integrated
part of the RCC slab.
Together with its crystalline
properties it will travel
into the capillaries,
pores, etc (reacting wherever
there is water) thus effectively
plugging the entire surface
making it water tight.
After the first layer
is applied and 24 hours
have elapsed the surface
will be wetted again and
then the second layer
will be applied. This
layer will extend 25 –
35 mm outside the line
where the Perlite Concrete
installation will be completed.
After a period of 6 hours
the surface will be ready
to take the installation
of Perlite Concrete.
Backing Plaster
on foam Glass :
A backing with vermiculite
plaster is spray applied
onto the foam glass vertical
surface upto a thickness
of 25 mm. Approx.
Waterproofing
on Backing Plaster :
Waterproofing with Koster’s
NB elastic system is nstalle
on the vertical surface
of the backing plaster
and allowed to air cure
for 24 hours.
Installation
of Perlite Concrete (
C ) : Perlite
Concrete of mix design
1 : 2.5 (by volume) will
then be installed as per
the drawing, in the area
from Y to X. The concrete
will be placed manually
with specially made implements
so as to push the concrete
right to the far end and
against the Backing lining
on the inner wall. The
concrete will be placed
in such a manner so that
there will remain a gap
at the top, ranging from
10 – 20 mm on the
far end – Y –
and 40 – 50 mm on
the outer end –
X . The outer surface
will be finished smooth.
Curing :
Perlite Concrete is will
be water cured for 7 days.
Drying :
The Perlite Concrete,
after the curing period,
must be dried thoroughly.
Installation of Modified
Perlite Concrete ( B )
: Perlite concrete of
mix design 1 : 2.5 ( by
volume ) and specified
modified with a bonding
emulsion and a plasticizer
especially designed for
this application, will
then be installed above
the first layer of Perlite
Concrete. This concrete
which will be sticky will
then be inserted into
the gap, deliberately
left during the previous
installation of the Perlite
Concrete, and will be
thoroughly compacted.
The outer surface will
be finished smooth.
Curing :
Wet Perlite concrete is
left in place to cure
for 7 days.
Drying :
The Perlite Concrete,
once again, after the
curing period must be
dried thoroughly.
Waterproofing
of the Outer Face of the
Perlite Concrete :
After the outer face of
the Perlite concrete has
been sufficiently smoothened
and dried. The surface
will be thoroughly wetted
and then the Koster’s
NB Elastic system will
be brush applied. This
system will be carefully
applied so as to ensure
that the application will
installed so as to extend
well on to the steel plate
on the top and extend
over the water proofing
layer already installed
on the surface of the
RCC base slab. After a
period of 24 hours the
surface will be wetted
thoroughly and then second
layer of NB Elastic will
be brush applied over
the first and after a
period of 24 hours the
whole system will be ready
to be handed over to the
customer. |